Newest Model Bear Den

The Bear Den is our newest model and is currently in the process of being built.  Stay tuned here or follow us on Facebook, #CLCBearDen to see progress photos and updates!

See all the finished photos, pricing and additional information!Finishing touches and punchlist items.  Appliances placed and final inspections and occupancy permit.Staircase installedWall, ceiling boards and trim completed.  First floor flooring started.Kitchen cabinet installationFurnace installation and testingSeptic installedDeck boards laid and deck structures finished.Deck piers installed

  • Finishing insulation in kitchen ceiling, and ceiling boards to prep kitchen for poly and flooring.
  • Installing ship lap on first floor.
  • Staining and applying poly to interior trim and doors.
  • Back filling is done and deck and porch posts are in.
  • Septic field is being excavated.

Propane tank installation.Floor, wall and ceiling insulation started.Well drilled, installed, and hooked-up.  Water is running.HVAC/Plumbing/Electrical continued.HVAC/Plumbing/Electrical rough in started.Interior walls are completed and windows installed.  Trusses are all placed and roof has been installed.Main cabin trusses are set.  Left gable wall logs are almost complete.Main log wall stacking complete and ready for gable logs and scissor trusses.  Trusses to be delivered and set next morning.All Advantech subfloor on the second story is complete.  Stacking of the second story logs has started.All floor trusses have been set.  Bedroom side ledger boards have been installed and first 2 rows of Advantech subfloor have been installed.Exterior staining of the first floor is complete.  Load bearing studwall has been installed and floor trusses have started to be installed.Two more deliveries of materials are received onsite.  The floor trusses for the 2nd floor and mechanical openings are also delivered.  Staining was started on the first floor.The first floor wall system is completed.May 6th, 2019 is the first official build day!

Flooring was completed and the log wall system started going up!As of May 3rd,  2019 all of the following have been completed:

  • Pier foundation placed and concreted

As of April 15th,  2019 all of the following have been completed:

  • Permits received
  • Driveway excavated and stoned
  • Cabin foundation excavation

As of January 15th,  2019 all of the following have been completed for lot preparation:

  • Design drawings finalized
  • Land purchased
  • Sewer survey
  • Rough stakeout of Bear Den
  • Driveway Stakeout
  • Application for sewer permit submitted
  • Application for driveway permit submitted
  • Tree removal lot clearing
  • Cutting in of driveway
  • Plot plan
  • Applied for zoning